Put every payment on a timeline first. The initial 1,000 is paid now, so its discount exponent is zero; future receipts must be moved back to today's date before adding them.
The undiscounted surplus is 200, but 200 is not NPV. Discounting gives 545.45 for the first receipt and 495.87 for the second, then subtracting today's cost gives 41.32.
A point beyond the slide: receiving the same positive amount later lowers its present value when the discount rate is positive. Move the second 600 to the end of year 3 and check whether the conclusion still holds.